Planned Dates vs Logic
Find the activities whose planned dates contradict the relationships the same schedule declares.
Not assignedEvidence detailsChecking
Planned Dates vs Logic content
Every relationship this schedule declares implies a date the successor may start. These are the activities whose planned dates do not satisfy that. A contradiction is a review signal, not a defect: actuals, soft logic and constraints all produce one lawfully, and this pass cannot tell you which.
Load a review to read the planned-date gaps.
The planned-gap chart appears once a review loads.
For the disturbances that make work late by a number of working days, each activity they act on is read against the time the planner left before its successor: enough room absorbs it, too little and the successor's planned start is overtaken. The planner's own dates, nothing recomputed; a counterfactual, not a forecast.
Choose a review to read its stress tests.
Review status and evidence steps
Steps of the decision on this page.